Foothills Medical Clinic Power Plant Expansion

Foothills Medical Clinic Power Plant Expansion Project

The Alberta Utilities Commission is currently reviewing an application for a power plant expansion at the Foothills Medical Clinic

Overview

The Alberta Utilities Commission is currently considering applications from Alberta Infrastructure, on behalf of Alberta Health Services for the Foothills Medican Centre Power Plant Expansion Project to expand the existing Foothills Medical Centre Power Plant and a connection to ENMAX Power Corporation’s existing distribution system to support the growth of the hospital and the future needs of the new cancer care facility that is currently under construction.

The AUC issued a notice of application for the Foothills Medical Centre Power Plant Project on December 14, 2018.

The expansion would consist of the addition of one 8-megawatt gas turbine generator, which would result in a total power plant generating capability of 23 megawatts. The additional equipment would be located in a new building on developed land next to the existing power plant located at 3133 Hospital Drive N.W., within the city of Calgary.

The existing power plant has been in operation for over 50 years and generates steam for heating, humidification, cooling and sterilization purposes at the buildings in the Foothills Medical Complex. Electricity is generated as a by-product of the steam generation and supplements the electricity supplied by ENMAX Power Corporation for use at the complex.

Submissions

The eFiling System should be accessed to view the applications and the other documents the AUC will be considering in this proceeding. The system is also used to file submissions and evidence to participate in the proceeding.

To create an account, select "New account" and follow the steps to create a user ID and password. If you have any questions about how to use the system please contact us at info@auc.ab.ca or 403-592-4500.

Documents being considered in this proceeding can be found in the eFiling System (which requires log in). Once you have logged in, enter 23958 in the "go to" section at the top left corner of your screen.

Have your say about a utility project has more information regarding your options for participation.

Proceeding 23958                Register

Application status: under review

Information session: January 16, 2019

Location: Four Points Sheraton Calgary West

 

Decision expected: Summer 2019

           

 AUC contact: Taylor McCusker 403-592-4438
or taylor.mccusker@auc.ab.ca      

 

 Alberta Infrastructure contact: Nick Pettipas 

403-875-0584 or nick.pettipas@gov.ab.ca 

                 

Listen to a hearing

Access all regulatory documents

Anyone can access applications and proceeding information through the eFiling System.

Create a new account or log in below