The Alberta Utilities Commission is currently reviewing an application for a 20.1-megawatt solar power plant east of Strathmore

Overview

The Alberta Utilities Commission is currently reviewing an application from East Strathmore Solar Project Inc. to construct and operate the East Strathmore Solar Project, a 20.1-megawatt solar power plant approximately 12 kilometres east of Strathmore. The proposed project would be sited on approximately 120 acres of private, cultivated land in Wheatland County on a single quarter section of land located in the southwest quarter of Section 9, Township 24, Range 23, west of the Fourth Meridian.

East Strathmore Solar Project Inc. has also applied to interconnect the power plant to the FortisAlberta Inc. electric distribution system through a 700-metre underground distribution line.   

The AUC will be holding a hearing for the East Strathmore Solar Project on March 31, 2020 in the William Andrew Grieve Hearing Room in Calgary.

The AUC will also be holding an information session on February 19, 2020 in Strathmore to provide information about how you may become involved in this proceeding and the funding which may be available to you to support your position. 


Submissions

The eFiling System should be accessed to view the applications and the other documents the AUC will be considering in this proceeding. The system is also used to file submissions and evidence to participate in the proceeding.

To create an account, select "New account" and follow the steps to create a user ID and password. If you have any questions about how to use the system please contact us at info@auc.ab.ca or 310-4AUC.

Documents being considered in this proceeding can be found in the eFiling System (which requires log in). Once you have logged in, enter 24266 in the "go to" section at the top left corner of your screen.

Have your say about a utility project has more information regarding your options for participation.

Proceeding 24266              Register

Application status: under review

 Hearing: March 31 - April 2, 2020, starting at 9 a.m.

Location: William Andrew Grieve Hearing Room

 

Information session: February 19, 2020, starting at 7 p.m.

Location: Days Inn & Suites, Strathmore, Alberta 

 

Decision expected: Summer 2020

           

 AUC contact: 
 Conrad Dalsin 403-592-3281
or conrad.dalsin@auc.ab.ca

 

 ATCO Gas and Pipelines Ltd. contacts: 
Adam Wood 780-420-5499
or
adam.wood@atco.com

Jo-Anne Van Sickle 780-420-7562
or joanne.vansickle@atco.com

                 