| Application number |
1607507 |
| Proceeding ID No. |
1368 |
| Applicant(s) |
Alberta Electric System Operator |
| Area |
Central |
| Description |
In its application, dated July 20, 2011, the AESO identifies the need for development and describes the proposed solution with respect to the electric system in the Red Deer region of Alberta to serve the existing and forecasted loads in the region. |
| AUC contact |
Sophie Jiang - 403-592-4418 or sophie.jiang@auc.ab.ca Trevor Wilde 403-592-4488 or trevor.wilde@auc.ab.ca |
| More information |
Click here to view further details of the application in our Proceeding Search System. |
| Become a registered participant |
Complete the submission form for NID applications and file it with the AUC |
The Commission has established the following process schedule to deal with the application
|
Process step |
Date |
|
Information session |
January 25, 2012 |
|
List of issues from interveners |
February 2 , 2012 |
|
Pre-hearing Conference |
February 9,2012 |
|
Pre-hearing Decision |
March 1, 2012 |
|
Information requests (questions) to applicant from interveners |
March 15, 2012 |
|
Responses from applicant to questions from interveners |
March 29, 2012 |
|
Filing of hearing evidence from interveners |
April 12, 2012 |
|
Information requests to interveners |
April 26, 2012 |
|
Responses from interveners to information requests |
May 10, 2012 |
|
Filing of reply evidence by applicant |
May 22, 2012 |
|
Commence hearing (9 a.m.) |
June 5 , 2012 |
Further information regarding the process steps can be found in the AUC's notice of pre-hearing conference and hearing or by contacting either of the AUC contacts above.