Combined needs identification document and transmission facility decisions

Combined transmission needs and facility decisions

Decisions on both the need and siting/routing for facility projects

 

Return to the facilities decision index page

​All new electric transmission facilities (with the exception of a small number of projects classified as critical transmission infrastructure) require two separate approvals from the AUC: (i) an approval of the need for new facilities as set out in a needs identification document (NID) filed by the Alberta Electric System Operator (AESO) under the Electric Utilities Act; and (ii) an approval of a facility application for the specific siting or routing of the new facilities, which is made by a transmission facility owner under the Hydro and Electric Energy Act. In NID applications, the AESO must demonstrate the need for new transmission, and propose a transmission solution to meet that need.  In a facility application, the Commission considers whether approval of the proposed facilities is in the public interest having regard to the project's social, economic and environmental effects. NID and facility applications may be considered by the Commission in separate proceedings (if considered independently, the facility proceeding must follow NID approval), or in a combined proceeding.

The issues typically considered in combined NID/facility decisions include:

  • The rationale for new transmission, including:
    • Generation or load growth
    • Reliability
    • System access service  
  • Choice of NID alternative – includes cost of alternative, routing issues, technical feasibility of alternative.
  • Consultation – includes adequacy, scope of consultation with landowners, other interested parties.
  • Property impacts – includes property value, agricultural impacts, business impacts, future development impacts.
  • Health and safety – includes electromagnetic frequency (EMF).
  • Routing and siting – includes route development, site/route choice (preferred vs alternative), transportation utility corridors, structure choice, construction impacts.
  • Environment – includes wildlife, plants, native prairie, water and water crossings.
  • Electrical effects includes pipeline interference and mitigation, stray voltage, radio frequency interference.
  • Project cost – includes costs of preferred vs alternative routes.
  • Noise includes noise impact assessment, post construction monitoring.
  • First Nations – includes consultation, impacts to constitutional rights.
  • Critical transmission infrastructure – whether facilities are critical transmission infrastructure as defined in the legislation.
  • Uncontested – applications with no outstanding objections, or objections were received and the AUC determined that the parties did not meet the test for standing.

 

Decisions for reference

  
  
  
  
  
Issues
  
21973-D01-2017Alberta Electric System Operator; AltaLink Management Ltd.Chestermere 419S and Balzac 391S Modification Need and Facility Applications21973Need: generation or load growth, Need: system access service, Consultation, Property impacts, Health and safety, Environment, Project cost, Noise
21761-D01-2017Alberta Electric System Operator; ATCO Electric Ltd. Hughes 2030S Substation21761Consultation, Property impacts, Health and safety, Routing and siting, Environment
21857-D01-2017Alberta Electric System Operator; AltaLink Management Ltd.Wainwright Transmission Reinforcement21857Need: reliability, Need: system access service, Consultation, Property impacts, Routing and siting, Environment, Electrical effects, Noise
21030-D02-2017Alberta PowerLine General Partner Ltd.Fort McMurray West 500-Kilovolt Transmission Project21030NID, Transmission lineConsultation, Property impacts, Health and safety, Routing and siting, Environment, Electrical effects, Noise, First Nations, Constitutional question, Critical transmission infrastructure
3386-D01-2016Alberta Electric System Operator; ENMAX Power CorporationFoothills Area Transmission Development in the South of Calgary3386NID, Transmission lineNeed: generation or load growth, Choice of NID alternative, Consultation, Property impacts, Health and safety, Routing and siting, Environment
20537-D01-2015Alberta Electric System Operator; Cenovus FCCL Ltd.Boreal 193S Substation20537NID, Transmission line, SubstationNeed: generation or load growth, Choice of NID alternative, First Nations
3598-D01-2015Alberta Electric System Operator; ATCO Electric Ltd. Whitetail Interconnection Project3598NID, Transmission lineNeed: generation or load growth, Choice of NID alternative
3543-D01-2015Alberta Electric System Operator; ATCO Electric Ltd.Carmon Creek Interconnection3543NID, Transmission line, SubstationNeed: generation or load growth, Need: reliability, Choice of NID alternative
2013-369Alberta Electric System Operator; AltaLink Management Ltd.; ENMAX Power CorporationFoothills Area Transmission Development2001NID, Transmission line, SubstationNeed: generation or load growth, Need: reliability, Choice of NID alternative, Constitutional question
2012-283Alberta Electric System Operator, ENMAX Power Corporation and AltaLink Management Ltd.East Calgary Transmission Project and Shepard Energy Centre Interconnection1229NID, Transmission line, SubstationNeed: generation or load growth, Choice of NID alternative
2012-220Alberta Electric System Operator, AltaLink Management Ltd. and ATCO Electric Ltd.Weasel Creek 947S and Abee 993 Substations and Transmission Line Project1363NID, Transmission line, SubstationNeed: generation or load growth, Choice of NID alternative, Consultation, Property impacts, Health and safety, Routing and siting, Environment, Electrical effects
2012-053Alberta Electric System Operator; ATCO Electric Ltd.Halkirk Wind Connection1092NID, Transmission line, SubstationChoice of NID alternative
2011-521Alberta Electric System OperatorTemporary Capacity Increase in Brintnell 876S Substation Wabasca/Brintnell Area208NID, Transmission line, SubstationNeed: generation or load growth
2011-340AltaLink Management Ltd.Transmission Line 904L West of Edmonton/Jackfish Lake Area754NID, Transmission line, SubstationProperty impacts, Health and safety, Routing and siting, Environment
2010-612Alberta Electric System Operator, AltaLink Management Ltd. and Alberta-Pacific Forest Industries Inc.Al-Pac Pulp Mill Project586NID, Transmission line, Substation, Power plant - Other generation sourceConsultation, Property impacts, Routing and siting, Environment, Noise
2010-338Fortuna GP, Inc.; Alberta Electric System Operator; ATCO Electric Ltd.Ghost Pine Wind Power Plant Project236NID, Transmission line, Substation, Power Plant - Wind PlantNeed: generation or load growth, Choice of NID alternative, Noise
2010-244Alberta Electric System Operator; AltaLink Management Ltd.Airdrie-Balzac Reactive Requirements Needs Identification Document Application and Addition of a Capacitor Bank at East Airdrie 199S Facility and at Dry Creek 186S Facility Applications250NID, SubstationUncontested
2010-182Alberta Electric System Operator and ATCO Electric Ltd.9L66 Line Relocation Transmission Development303NID, Transmission lineUncontested
2010-095Alberta Electric System Operator; AltaLink Management Ltd.; ATCO Electric Ltd.Buffalo Creek 526S Substation Upgrade262NID, Transmission line, SubstationUncontested
2010-099Alberta Electric System Operator; AltaLink Management Ltd.AESO Need Identification Document Application to Alter Cold Creek 602S Substation and AltaLink Application to Alter Cold Creek 602S Substation373NID, SubstationUncontested
2010-057Alberta Electric System Operator; ENMAX Power CorporationCalgary Business District Underground Cable Replacement277NID, Transmission LineNeed: generation or load growth
2010-015Alberta Electric System Operator; ATCO Electric Ltd.New Lindbergh 969S Substation, Transmission Line and Related Facilities254NID, Transmission lineNeed: generation or load growth, Choice of NID alternative
2003-027ATCO Electric Ltd.Dover to Deerland Fort McMurray/ Fort Saskatchewan Areas - Phase I Decision Need for FacilitiesNID, Transmission line, SubstationNeed: generation or load growth, Choice of NID alternative