This report is automatically generated from the eFiling System

Current applications

The current applications tool below lists all applications that are currently active with the AUC. You are able to enter search criteria to find a specific active application. This tool will only give general information about the application. For more detailed information or to access the full proceeding please log-in to the AUC's eFiling System.

  
  
  
  
  
23508-A00123223 - EEC 2016-2018 EPSP Compliance Filing - CCA Cost Claim2018-04-19Consumers Coalition Of Alberta23508
23507-A001Approval of the Franchise Agreement between ATCO Gas and Pipelines Ltd and the Village of Wabamun2018-04-19ATCO Gas North23507
23505-A001AUC-initiated review and variance of Decision 22741-D1-20182018-04-18Alberta Utilities Commission23505
23503-A004ATCO Gas and Pipelines Ltd. (South) Licence 23379 - De-Licence Line 12018-04-17ATCO Gas and Pipelines Ltd. (SOUTH)23503
23503-A003ATCO Gas and Pipelines Ltd. (South) Licence 5341 - De-Licence Line 132018-04-17ATCO Gas and Pipelines Ltd. (SOUTH)23503
23503-A002ATCO Gas and Pipelines Ltd. (South) Licence 2594 - De-Licence Lines 101,102,114,115,123,270 and 2712018-04-17ATCO Gas and Pipelines Ltd. (SOUTH)23503
23503-A001ATCO Gas and Pipelines Ltd. (South) License 1670 - De-Licence Lines 3 and 42018-04-17ATCO Gas and Pipelines Ltd. (SOUTH)23503
23494-A002DERS 2017-2018 DRT and RRT Application Cost Claim2018-04-12Direct Energy Marketing Limited23494
23501-A002ATCO Gas and Pipelines Ltd. (South) Lic 7016 - Line Split - Removal2018-04-16ATCO Gas and Pipelines Ltd. (SOUTH)23501
23501-A001ATCO Gas and Pipelines Ltd. (South) Licence 5923 - Line Split - Removal - Installation2018-04-16ATCO Gas and Pipelines Ltd. (SOUTH)23501
23500-A001EEC EPSP 2018 Q1 Cost Claim2018-04-13ENMAX Energy Corporation23500
23496-A001CCA Complaint to the AUC re Conduct of AESO2018-04-12Consumers Coalition Of Alberta23496
23495-A001ENMAX Power Corporation Letter of Enquiry ENMAX No. 22 Substation – Transmission Reliability Upgrade2018-04-12ENMAX Power Corporation23495
23494-A00122004 - DERS RRT and DRT - CCA Cost Claim2018-04-11Consumers Coalition Of Alberta23494
23492-A001EEA 2018-2021 Energy Price Setting Plan Compliance Filing2018-04-10Epcor Energy Alberta Gp Inc.23492
23491-A001ATCO Gas and Pipelines Ltd. (South) Licence 1594 - Line Split - Removals2018-04-10ATCO Gas and Pipelines Ltd. (SOUTH)23491
23479-A004ENMAX Power Corporation Motion for a Review and Variance of Decision 20414-D01-2016 (Errata)2018-04-06ENMAX Power Corporation23479
23479-A003ENMAX Power Corporation Review and Variance of Decision 22394-D01-20182018-04-06ENMAX Power Corporation23479
23479-A002ATCO Utilities R&V to Decision 22394-D01-20182018-04-06ATCO Gas North23479
23490-A001ATCO Gas and Pipelines Ltd. (South) Licence 8981 - Line Split Line 1 and Remove Line 22018-04-09ATCO Gas and Pipelines Ltd. (SOUTH)23490
23487-A00121608 - ATCO Gas Z Factor Recovery - CCA Cost Claim2018-04-06Consumers Coalition Of Alberta23487
23475-A00223114 - AET 2013-2014 Transmission Deferral Account - CCA Cost Claim2018-04-05Consumers Coalition Of Alberta23475
23486-A00123220  AUI Terms and Conditions of Service - CCA Cost Claim2018-04-06Consumers Coalition Of Alberta23486
23479-A001FortisAlberta Application for a Review and Variance of Decision 22394-D01-2018 (Rebasing Compliance Filing)2018-04-06FortisAlberta Inc.23479
23456-A003AML Fortis East Crossfield Substation Upgrade2018-03-29AltaLink Management Ltd.23456
23456-A002AML Fortis East Crossfield Substation Upgrade2018-03-29AltaLink Management Ltd.23456
23475-A001AET 2013-2014 Deferral Account Compliance Application - Cost Claim2018-04-04ATCO Electric Ltd.23475
23471-A001ENMAX Power Corporation ENMAX No. 11 Substation Alteration Request for Time Extension to Permit and Licence 22624-D02-20172018-04-04ENMAX Power Corporation23471
23470-A001Forwarding Notice for Proposed new INT Standards, Retirement of existing INT Standards, and Retirement of reliability standards previously assessed non-applicable in Alberta INT Standards. 2018-04-03Independent System Operator23470
23469-A001ATCO Electric's application to rebuild the Kinuso Substation2018-04-03ATCO Electric Ltd.23469