Dunmore Solar Project

​Dunmore Solar Project

The AUC has approved​ applications for a solar power plant and a substation near the city of Medicine Hat 

 





​​
​​



​​

​​​







​​​​​​​​​​​​​​​

​​​

Overview​

The Alberta Utilities Commission has approved applications for the Dunmore Solar Project, consisting of a solar power plant and a substation near the city of Medicine Hat. The AUC released a notice of applications for the project on May 11, 2021.

Dunmore Solar Inc. has been approved to construct and operate the 216-megawatt Dunmore Solar Power Plant and associated Dunmore 1011S Substation. The project will be located on 623 acres of privately owned agricultural land, approximately 10 kilometres northeast of the hamlet of Dunmore and 13 kilometres east of the city of Medicine Hat in Cypress County, Alberta. Specifically, the project area will cover the following sections: 

​Quarter Section
​Section
​Township
​Range
​Meridian
​NE and SE
​33
​12
​4
​W4M
​NW and SW
​34
​12
​4
​W4M
​NW, NE, SE and SW
​27
​12
​4
​W4M


The Dunmore 1011S Substation will be located on the southeast quarter Section 33, Township 12, Range 4, west of the Fourth Meridian.

Virtual hearing 

The AUC issed a notice of hearing cancellation​ for Proceeding 26485 on August 19, 2021. 

The Commission issued a notice of hearing for Proceeding 26485 on July 7, 2021, after it had determined that Stan Weiss, Dayna Felesky and Felesky Cattle Co. Ltd. (represented by Dayna Felesky) met the test for standing under Section 9(2) of the Alberta Utilities Commission Act. No other persons requested standing in the proceeding. 

The Commission cancelled the hearing because Stan Weiss and Dayna Felesky (for herself and for Felesky Cattle Co. Ltd.) each filed letters with the Commission stating that they wished to formally withdraw their objections to the Dunmore Solar Energy Project because their concerns have been addressed by Dunmore Solar Inc., and that no further AUC process or conditions are necessary in order to address their concerns.

The eFiling System​

The eFiling System should be accessed to view the applications and the other documents the AUC will be considering in this proceeding. The system is also used to file submissions and evidence to participate in the proceeding.

To create an account, select "New account" and follow the steps to create a user ID and password. If you have any questions about how to use the system please contact us at info@auc.ab.ca or 310-4AUC.

Documents considered in this proceeding can be found in the eFiling​ System (which requires log in). Once you have logged in, enter 2648​5​​ in the "go to" section at the top left corner of your screen. 



Proceeding 26485               Register

Application status: completed

Decision: 26485-D01-2021, issued September 9, 2021

 

AUC contact: Joan Yu
 403-592-4380 or joan.yu@a​uc.ab.ca​​

​​

 ASCENT Energy Partners Ltd. contact: Jennifer Traichel 587-216-0696 or jennifer@ascentpartners.ca​​