Rule
Rule 024: Rules Respecting Micro-Generation
Effective date
July 16, 2019
Description
Rule 024 applies to customers who intend to generate energy for their own use from a micro-generation generating unit that is capable of generating up to five megawatts of energy. The rule sets out the requirements that must be met before constructing and interconnecting a micro-generation unit to the distribution grid. It also sets out a process for disputes between micro-generation customers and the applicable wire owner regarding the costs to connect to the grid.
Consultations
Rule 024 consultation page
Rule 024 blacklined version
Forms
Form A - Micro-generation notice
Form B - Notice of dispute
Form C - Notice of complaint
Reference information
Micro-generation notice submission guideline
Additional information about micro-generation
Distributed-generation application guideline