Standing decisions

Standing decisions

Decisions on whether or not parties have standing to participate in a proceeding

​​​​​​ Return to the facilities decision index page

The AUC must hold a public hearing on an application if persons who have filed a statement of intent to participate in a proceeding demonstrate that they have rights that may be directly and adversely affected by the AUC's decision. Such a person may fully participate in the hearing, including giving written evidence, written or oral questioning of witnesses adverse in interest, and providing argument. This permission to participate is referred to as standing.

Section 9(2) of the Alberta Utilities Commission Act sets out how the AUC must determine standing, which involves a two-part test which is considered by the AUC in each proceeding before it. Examples of the AUC's rulings on standings have been provided in this category, starting in 2014. The issues typically considered in standing applications include:

  • Property rights
  • Proximity
  • Business interests
  • Aboriginal rights
  • Participation without standing
  • Ratepayer interests
  • No direct or adverse effect

Decisions for reference

  
  
  
  
  
Issues
  
25469-F0141Alberta Electric System Operator; ATCO Electric Ltd.; AltaLink Management Ltd.  Ruling on standing25469NID, transmission line, transmission interconnection, substationProperty rights, Proximity, Ratepayer interests
25469-F0143Alberta Electric System Operator; ATCO Electric Ltd.; AltaLink Management Ltd.  Ruling on standing of the Blood Tribe25469NID, transmission line, transmission interconnection, substationAboriginal rights
25469-F0144Alberta Electric System Operator; ATCO Electric Ltd.; AltaLink Management Ltd.  Ruling on standing of the Ermineskin Cree Nation 25469NID, transmission line, transmission interconnection, substationAboriginal rights
25951-F0010SunAlta Solar Inc.Ruling on standing 25951Power plant, power plant interconnectionProperty rights, Proximity
25469-F0134Alberta Electric System Operator; ATCO Electric Ltd.; AltaLink Management Ltd.  Ruling on standing25469NID, transmission line, transmission interconnection, substationProperty rights, Proximity
25469-F0124Alberta Electric System Operator; ATCO Electric Ltd.; AltaLink Management Ltd. Ruling on Consumers’ Coalition of Alberta’s standing and comments on budget 25469NID, transmission line, transmission interconnection, substationRatepayer interests
25469-F0122Alberta Electric System Operator; ATCO Electric Ltd.; AltaLink Management Ltd.  Ruling on standing 25469NID, transmission line, transmission interconnection, substationProperty rights, Proximity
25469-F0102Alberta Electric System Operator; ATCO Electric Ltd.; AltaLink Management Ltd. Ruling on standing of Métis Nation of Alberta25469NID, transmission line, transmission interconnection, substationAboriginal rights
25469-F0097Alberta Electric System Operator; ATCO Electric Ltd.; AltaLink Management Ltd. Central East Transfer-out Transmission Development Needs Identification Document; Central East Transfer-out Transmission Development Facility Applications25469NID, transmission line, transmission interconnection, substationProperty rights, Proximity
25100-F0021Capstone Infrastructure CorporationBuffalo Atlee 1, 2 and 3 Wind Power Plants 25100Power plantProperty rights, Proximity
25690-F0012Barlow Solar Park Ltd.Barlow Solar Project25690Power plantNo direct or adverse effect
22843-F0047BER Hand Hills Wind GP Inc.Amendment to the BluEarth Hand Hills Wind Project22843Power plant, power plant ownership change, transmission ownership changeProperty rights, Proximity
25074-F0065Alberta Electric System Operator; Windrise Wind Energy Inc.; AltaLink Management Ltd.Windrise Connection Project25074NID, transmission line, substation, transmission interconnectionProperty rights, Proximity
25018-F0050BHE Canada Rattlesnake G.P. Inc.Rattlesnake Ridge Wind Power Project25018Power plant – wind plant, substation, interconnection, transmission line, NIDProperty rights
25346-F0017Solar Krafte Utilities Inc.Solar Krafte Strathmore Solar Project25346Power plant – solar plantProperty rights, Proximity
25296-F0039Aura Power Renewables Ltd.Fox Coulee Solar Project Amendment25296Power plantProperty rights, Proximity
25206-F0018ENMAX Power CorporationNo. 1 Substation Replacement Project25206Substation, transmission line, transmission interconnectionProperty rights, Proximity, Ratepayer interests
25140-F0017AltaLink Management Ltd.Red Deer Area Transmission Development – Decommission and Salvage of Remaining Portions of Transmission Lines 80L and 716L25140Transmission lineProperty rights, Proximity, Aboriginal rights, No direct or adverse effect
25170-F0010Irricana Power GenerationIrricana Solar Project25170Power plant, interconnectionProperty rights, Proximity
25047-F0073Capital Power Generation Services Inc.Halkirk 2 Wind Power Project Time Extension25047Power plant – wind plant, transmission lineNo direct or adverse effect
25074-F0025Alberta Electric System Operator; Windrise Wind Energy Inc.; AltaLink Management Ltd.Windrise Connection Project25074NID, transmission line, substation, transmission interconnectionProperty rights, Proximity
23958-F0039Alberta InfrastructureFoothills Medical Centre Power Plant Expansion Project23958Power plant, power plant interconnectionNo direct or adverse effect
25181-F0009ATCO Electric Ltd. Rycroft 730S Substation Expansion25181Substation, transmission lineProperty rights, Proximity
25018-F0024BHE Canada Rattlesnake G.P. Inc. Rattlesnake Ridge Wind Power Project25018NID, Power plant -wind plant, substation, transmission line, power plant inter connectionProperty rights, Proximity
25018-F0021BHE Canada Rattlesnake G.P. Inc. Rattlesnake Ridge Wind Power Project25018NID, Power plant -wind plant, substation, transmission line, power plant inter connectionProperty rights, Proximity
25034-F0018Northstone Power Corp. Application to Alter Northstone Elmworth Generation Station   25034Power plantProperty rights, Proximity
24827-F0076ATCO Gas and Pipelines Ltd. Northwest Calgary Connector Pipeline Project 24827Pipeline - newProperty rights, Proximity
23958-F0030Alberta InfrastructureFoothills Medical Centre Power Plant Expansion Project 23958Power plant, power plant interconnectionProperty rights, Proximity
23796-F0036Prosper Petroleum Ltd. Rigel Oil Sands Project Co-Generation Facility 23796Power plant, ISDAboriginal rights
24827-F0048ATCO Gas and Pipelines Ltd. Northwest Calgary Connector Pipeline Project 24827Pipeline - newProperty rights, Proximity