Applications 28906-A001, 28906-A002, 28906-A003, 28906-A004, 28906-A005 and 28906-A006

Commencement of virtual hearing: September 22, 2025, at 10 a.m.

Overview

The Alberta Utilities Commission (AUC), the independent utilities regulator will be considering an application by Enfinite for the construction and operation of a 100-megawatt battery storage facility called Laramide Battery Storage Facility. This application has been filed under Section 13.01 and 18 of the Hydro and Electric Energy Act.

Additional information about the application:

  • The Project would be located at SE-18-19-27-W4M in Foothills County, Alberta, northwest of the AltaLink owned Foothills 237S Substation.
  • The Project would be interconnected through a new 240-kilovolt (kV) transmission line to the Foothills 237S Substation.
  • During periods of low demand on the electrical system, the Laramide BSF would pull electricity from the system and charge the batteries. The batteries would add reliability to the Alberta Interconnected Electric System (AIES), including responding at times of higher demand, or during outages of other system elements.
  • The total name plate capacity of the Project is 100 MW. The batteries can discharge at a maximum rate of 100 MW for four (4) hours providing a total storage capacity of 400 MWh.

Components of the Project would include:

  • 105 lithium-ion battery modules with inverters
  • One 240-kV transformer
  • 27-kV to 34.5-kV transformers
  • An approximately one KM 240 kV transmission line
  • Control building (with associated protection and controls equipment)
  • Fencing
  • Access and internal roadways
  • Underground power/control cables

The project area can be seen here.

Hearing information

A notice of hearing for this proceeding was issued on May 23, 2025. The hearing is scheduled to begin on September 22, 2025. To learn more about the review process, or for more information about how you may become involved in this proceeding, please contact us or visit the following webpages:

Summarized process schedule

The AUC has established the following process to consider the applications:

Process step Date
Virtual participant information session June 3, 2025, at 6 p.m.
Deadline for interveners to file information requests (questions) to the applicants June 9, 2025
Applicants’ deadline to respond to information requests June 23, 2025
Interveners’ written evidence deadline July 7, 2025
Information requests to interveners about intervener evidence July 23, 2025
Interveners deadline to respond to information requests  August 12, 2025
Applicants’ reply evidence deadline August 25, 2025
Virtual connection test session September 15, 2025
Commencement of virtual oral hearing October 22, 2025, at 9 a.m.

The eFiling System 

The eFiling System should be accessed to view the applications and the other documents the AUC will be considering in this proceeding. The system is also used to file submissions and evidence to participate in the proceeding.

To create an account, select “New account” and follow the steps to create a user ID and password. If you have any questions about how to use the system please contact us at info@auc.ab.ca or 310-4AUC.

Documents being considered in this proceeding can be found in the eFiling​ System (which requires log in). Once you have logged in, enter 28906 in the “go to” section at the top left corner of your screen.​

Laramide Battery Storage Facility Application
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.