Overview

The AUC will be considering the power plant, substation and energy storage facility development applications in Proceeding 29226.

Fox Meadows Wind Inc. has applied to construct and operate a wind power plant and associated Spalding 1059S Substation and energy storage facility. The applications have been filed under the Hydro and Electric Energy Act. The power plant would consist of 25 wind turbines, with a total generating capability of 165 megawatts. The project turbines would have a hub height of 115 metres and a rotor diameter of 162 metres. The power plant would also include an underground collector system, which would be used for collecting the electric energy generated by each turbine and transmitting the electric energy to the proposed Spalding 1059S Substation.

The project would be located in the Municipal District of Wainwright No. 61 and Municipal District of Provost No. 52, approximately 17 kilometres south of the village of Edgerton and approximately 20 kilometres north of the town of Provost. Specifically, the project would be located within townships 41 and 42, ranges 3 and 4, west of Fourth Meridian.

The Spalding 1059S Substation and energy storage facility would be located in the southeast quarter of Section 2, Township 42, Range 4, west of the Fourth Meridian.

Hearing Information

The AUC will be holding a hearing for this proceeding. The hearing will commence on Tuesday, February 24, 2025, at 10 a.m.

To learn more about the review process, or for more information about how you may become involved in this proceeding, please contact us or visit the following webpages:

Summarized process schedule

The AUC has established the following process to consider the applications:

Process step Date
Interveners’ information requests (IRs) to applicant November 8, 2024
Applicant’s responses to interveners’ IRs November 22, 2024
Interveners’ written evidence December 6, 2024
Applicant’s and Commission’s IRs to interveners December 23, 2024
Interveners’ responses to Applicant’s and Commission’s IRs January 13, 202
Applicant’s written reply evidence January 27, 2025
Commencement of hearing Tuesday, February 24, 2025, 10 a.m.

The eFiling System​

The eFiling System should be accessed to view the applications and the other documents the AUC will be considering in this proceeding. The system is also used to file submissions and evidence to participate in the proceeding.

To create an account, select “New account” and follow the steps to create a user ID and password. If you have any questions about how to use the eFiling System please contact us at info@auc.ab.ca or 310-4AUC.

Documents being considered in this proceeding can be found in the eFiling​ System (which requires log in). Once you have logged in, enter 29226 in the “go to” section at the top left corner of your screen.

Fox Meadows Wind Project
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.