Proceeding 29538  Register

Application 29538-A001

Commencement of virtual hearing: June 2, 2025, at 10 a.m. 

 

Watch an AUC hearing

Overview

The AUC will be considering the transmission line application in Proceeding 29538.

The City of Medicine Hat has applied to rebuild approximately 20 kilometres of existing 69-kilovolt (kV) transmission lines 30L and 40L between the NE Crescent Heights MHS-5 Substation and the Southridge MHS-3 Substation. The City proposed to rebuild the lines at a 138-kV standard but to initially operate the lines at 69 kV. The application has been filed under the Hydro and Electric Energy Act.

Map images showing proposed location of the project in the Medicine Hat area.

Hearing Information

The AUC issued a notice of hearing for this proceeding on January 17, 2025. The hearing is scheduled to begin on June 2, 2025, at 10 a.m.

To learn more about the review process, or for more information about how you may become involved in this proceeding, please contact us or visit the following webpages:

Summarized process schedule

The AUC has established the following process to consider the applications:

Process step Date
Interveners’ information requests (questions) to applicant deadline February 28, 2025
Applicant’s deadline to respond to information requests March 14, 2025
Interveners’ written evidence deadline March 28, 2025
Information requests to interveners about intervener evidence April 11, 2025
Interveners’ deadline to respond to information requests April 25, 2025
Applicant’s written reply evidence deadline May 9, 2025
Commencement of hearing June 2, 2025, at 10 a.m.

The eFiling System​

The eFiling System should be accessed to view the applications and the other documents the AUC will be considering in this proceeding. The system is also used to file submissions and evidence to participate in the proceeding.

To create an account, select “New account” and follow the steps to create a user ID and password. If you have any questions about how to use the eFiling System please contact us at info@auc.ab.ca or 310-4AUC.

Documents being considered in this proceeding can be found in the eFiling​ System (which requires log in). Once you have logged in, enter 29538 in the “go to” section at the top left corner of your screen.

East Ring Enhancement Project – Transmission Lines 30L and 40L Rebuild
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.