Proceeding 30518  Register

Application 30518-A001

Overview

The AUC is considering the power plant development application in Proceeding 30518.

Heartland Power Generation LP has applied to construct and operate the Beacon AI Centers – Heartland Project Thermal Power Plant. The project is proposed to be located within the Alberta Industrial Heartland, approximately seven kilometres east of Gibbons, in Sturgeon County, Alberta. Specifically, the project would be located in Section 15, Township 56, Range 22, west of the Fourth Meridian.

The total capability of the project would be 920 megawatts, and under normal operating scenarios, would supply approximately 800 megawatts of power to co-located, on-site data halls, intended to contain artificial-intelligence and high-performing-computing facilities.

The application has been filed under the Hydro and Electric Energy Act.

Written hearing

The AUC held a written hearing to review the application and submissions received to consider the power plant development application in Proceeding 30518.


The eFiling System​

The eFiling System should be accessed to view the applications and the other documents the AUC will be considering in this proceeding. The system is also used to file submissions and evidence to participate in the proceeding.

To create an account, select “New account” and follow the steps to create a user ID and password. If you have any questions about how to use the eFiling System please contact us at info@auc.ab.ca or 310-4AUC.

Documents being considered in this proceeding can be found in the eFiling​ System (which requires log in). Once you have logged in, enter 30518 in the “go to” section at the top left corner of your screen.

Beacon AI Centers – Heartland Project Thermal Power Plant Application