Proceeding 30261  Register

Application 30261-A001

Decision 30261-D02-2026 issued on June 25, 2026.

Watch an AUC hearing

Overview

The AUC has approved the power plant development application in Proceeding 30261.

Greenlight Electricity Centre GP Ltd. has applied to construct and operate an 1,864-megawatt (MW) combined-cycle power generation facility. The project is proposed to be located in the Alberta Industrial Heartland on 98 hectares of private land, approximately 8.5 kilometres east of Gibbons, Alberta. Specifically, the project would be located in the east half of Section 10, Township 56, Range 22, west of the Fourth Meridian. The project is proposed to be developed in two stages and anticipated to be fully developed and operational in 2031. The application has been filed under the Hydro and Electric Energy Act.

The eFiling System​

The eFiling System should be accessed to view the applications and the other documents the AUC will be considering in this proceeding. The system is also used to file submissions and evidence to participate in the proceeding.

To create an account, select “New account” and follow the steps to create a user ID and password. If you have any questions about how to use the eFiling System please contact us at info@auc.ab.ca or 310-4AUC.

Documents being considered in this proceeding can be found in the eFiling​ System (which requires log in). Once you have logged in, enter 30261 in the “go to” section at the top left corner of your screen.

Greenlight Electricity Centre